EXTREMELY LOUD CONSTRUCTION NOISE FROM CONTINUOUS JACK-HAMMERING
SDCI Notes: INT INSP 4/26/16 DG I WAS AT THE SITE AND SAW INFRASOURCE BREAKING CONCRETE AND DIGGING IN THE STREET ROW. THE CONTRACTOR WHO IS BUILDING A NEW BUILDING AT 414 RAVENNA WAS ALSO BREAKING CONCRETE, TO CONNECT TO PSE'S GAS LINE. THE CONTRACTOR WASN'T AROUND, BUT HIS IMPACT TOOLS WERE LAYING NEXT TO HIS BUILDING. THE COMPLAINT ISN'T ABOUT AN EARLY START, BUT CONTINUOUS JACKHAMMERING. I WILL CALL COMPLAINANT. INFRASOURCE STARTED TODAY AT 9AM, THE COMPLAINT CAME IN ON FRIDAY LAST WEEK. MUST BE THE BUILDING CONTRACTOR WHO SHE IS COMPLAINANT ABOUT.I CALLED COMPLAINANT,SHE SAID THEY DIDN'T START EARLY, IT JUST WENT ON ALL DAY. I GAVE HER THE HOURS AND MY EMAIL ADDRESS IN CASE THEY START TOO EARLY OR GO LATE.5/31/16 DG NO COMPLAINTS IN 30 DAYS, VC.
COMPLETED
·
Inspection: 2016-04-26
·
Result: COMPLETED